The administrative court of Saint-Martin delivered its deliberations on June 12 in the case opposing the prefecture and the Collectivity concerning the lands acquired for the extension of the airport runway and the deviation of the Grand-Case road ; he rejected the prefecture's request.
The latter had asked the court to cancel the deliberation of December 20, 2016 of the executive council on the acquisition of land for the extension of the airport runway and the deviation of the Grand-Case road because it considered in particular that the COM had committed a manifest error of assessment by deciding to acquire the plot at a price approximately 60% higher than the valuation of France Domaine, that is to say an excess of 2,5 million euros. (More details on www.soualigapost.com)
No comments