Safety: Work begins on the roadway at Cripple Gate on August 13!

0

The community of Saint-Martin will launch work on the roadway at the crossing of Cripple Gate (entrance to Colombier), starting Monday, August 13, 2018.

This work will take place over 15 days and will consist of installing crash barriers and protective curbs for pedestrians. The cost of the works is € 169. Alternate road traffic will be in place for the first 202.00 days.

The community of Saint-Martin apologizes in advance for the inconvenience caused.